OpenPlant PID Help

To Change the Pipeline of a Pipe Run

  1. Select the Change Pipe Run's Pipeline option from the Piping Utilities gallery.
  2. Click on one of the pipe runs in the drawing belonging to the pipeline you want to set for the pipe run.
  3. Next, select the pipe run whose pipeline is to be changed.
  4. Left-click to Accept the selection. (A right-click here will cancel the command.) The pipe run will be added to the pipeline and will inherit the pipeline's cad properties.

    To check this, you can click on one of the pipeline's runs and notice that the new run will highlighted along with it. If you open the Element Info dialog, the run will be listed at the top of the dialog with the other pipe runs associated with the pipeline.

    Note: If the pipe run being added has the same name as an existing pipe run on the pipeline, then the added run's name will be changed to be unique.